This decision has important implications for parties to voluntary planning agreements.

AustraliaReal Estate and Construction

On 8 December 2011, the Court of Appeal handed down judgment in Huntlee Pty Ltd and Minister for Planning and Infrastructure v Sweetwater Action Group Inc [2011] NSWCA 378 overturning the decision of the Biscoe J in the Land and Environment Court declaring the rezoning of the Huntlee New Town Site invalid.

The decision has important implications for parties to voluntary planning agreements.

SUMMARY

  • Registration of a voluntary planning agreement (VPA) may be a suitable means of enforcement under the Environmental Planning & Assessment Act, 1979 (EPA Act).
  • Each planning authority must assess the developer's obligations in a VPA and consider whether a means of enforcement offered by the developer is likely to eliminate or reduce to a commercially acceptable level the risk that each VPA obligation will not be performed. This assessment should take account of the: