We previously reported about this case in the Tribunal where an
estoppel was granted ordering the landlord to execute a lease. Even
though no commencement date was agreed, the landlord had agreed to
grant a lease and provided draft documents to the tenant. The
tenant promptly executed these and began renovating the premises.
The landlord did not indicate to the tenant that they did not
intend to execute the lease, and watched the tenant spend money
renovating the premises. Both parties have appealed the
decision.
Can a landlord watch a tenant refurbish a premises and
then decide not to grant the lease?
Risi Pty Ltd v Pin Oak Holdings Pty td [2017] VSCA
317
The Tribunal ordered the landlord to sign the lease – this
would tie up the property for 13 years. The landlord appealed to
the Supreme Court of Victoria, and argued first, that there were no
grounds to find an estoppel, and second, that even if there were,
compensation would be an adequate remedy for the