A builder was held liable in negligence to a body corporate of commercial premises, despite no contractual relationship.

AustraliaReal Estate and Construction

The NSW Court of Appeal recently held that a builder was liable in negligence to a body corporate of commercial premises for defects which posed a risk to health and safety, despite there being no contractual relationship between the body corporate and the builder and the body corporate not being in existence at the time of construction.

Background

The Chelsea Apartments at Chatswood comprise 9 floors of serviced apartments and 12 floors of residential apartments ('development').

Multiplex was engaged to design and construct the development.  The developer had also entered an agreement with three separate Stockland entities under which the serviced apartments could be sold to investors by Stockland, which continued to manage the serviced apartment business.