Are you prepared for an adjudication during the Christmas closure period?

Corrs Chambers Westgarth
Corrs Chambers Westgarth
Contributor
Corrs Chambers Westgarth

Corrs Chambers Westgarth

Corrs Chambers Westgarth is Australia’s leading independent law firm. We provide exceptional legal...

View firm profile
Explore more from Corrs Chambers Westgarth

Unlike proceedings in many courts and tribunals, the time periods for adjudications do not stop in the Christmas season.

AustraliaReal Estate and Construction

If you are involved in a contract under which there is likely to be a dispute over a payment claim then you may be at an increased risk of receiving an adjudication application under the Construction Contracts Act 2004 (WA) over the Christmas period.

WHAT IS THE PROBLEM?

Unlike proceedings in many courts and tribunals, the time periods for adjudications do not stop running during the Christmas season.

Some contractors (and their lawyers) attempt to take advantage of this fact by serving their application for adjudication on respondents during the Christmas closure period so that they can obtain a tactical advantage by catching you out while people are on leave.

WHY IS THIS A PROBLEM?