This case gives guidance about exercise of the Court's discretion to grant leave to enforce adjudication determinations.

AustraliaReal Estate and Construction

The recent Western Australian Supreme Court decision in Delmere Holdings Pty Ltd v Green [2015] WASC 148 is interesting for three reasons.

First, it is an example of the Court emphasing the importance of defining carefully what is alleged to be the 'payment claim' and the 'payment dispute' in an application for adjudication under the Construction Contracts Act 2004 (WA) (Act).

Second, the decision provides further (although not conclusive) guidance on what constitutes a 'payment claim' for the purposes of s 3 of the Act.

Third, it is another example of the Court quashing an adjudication determination on the basis of jurisdictional error committed by a non-legally trained adjudicator.1

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from