The Victorian Court of Appeal has provided further guidance in relation to how a contractual duty of good faith operates.

AustraliaReal Estate and Construction

In the recent decision of Masters Home Improvement Pty Ltd v North East Solutions Pty Ltd [2017] VSCA 88, the Victorian Court of Appeal provided further guidance in relation to how a contractual duty of good faith operates.

North East Solution Pty Ltd (NES) had entered into an Agreement for Lease (the Agreement) with Masters and its parent company Woolworths, with Woolworths providing a guarantee for Masters' obligations. The Agreement set out that NES was to construct a hardware store at its own cost (the Landlord's Works Costs), and provided for the grant of a lease for an initial period of 12 years, followed by a number of options exercisable at Master's discretion.

The Agreement set out that NES and Masters "acting reasonably and in good faith" must attempt to resolve any differences they may have in relation to: