Share on LinkedInShare on LinkedIn

ARTICLE · 21 SEPTEMBER 2013

Federal Court considers the scope of carriers’ access and installation powers contained in the Telecommunucations Act

Corrs Chambers Westgarth
Corrs Chambers Westgarth
Contributor
Corrs Chambers Westgarth

Corrs Chambers Westgarth

Corrs Chambers Westgarth is Australia’s leading independent law firm. We provide exceptional legal...

View firm profile
Explore more from Corrs Chambers Westgarth

The case considered if a licensed carrier was authorised by a LAAN to access land to install two fibre optic cables.

AustraliaMedia, Telecoms, IT, Entertainment

NEED TO KNOW

On 16 May 2013, Justice Tracey, in the Federal Court, handed down his decision in Pipe Networks Pty Ltd v Commonwealth Superannuation Corporation, 1 a case relating to the construction of Schedules 1 and 3 of the Telecommunications Act 1997 (Cth) (the Act).

Schedule 1 of the Act sets out a regime for one carrier to access another carrier's facilities on agreed or arbitrated terms, which normally include a fee for access. Schedule 3 provides carriers with statutory powers to require a land owner / occupier to provide access to land in order for the carrier to install, operate and maintain facilities.

The case considered whether PIPE Networks Pty Limited (PIPE), a licensed carrier, was authorised by a land access and activity notice (LAAN) issued under Schedule 3 of the Act to install two fibre optic cables in the building at 101 Collins Street, Melbourne (the Building) and, if so, whether it still needed to negotiate the terms of access Part 3 of

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.