ARTICLE · 12 NOVEMBER 2011

Pre-emptive Strike: Adelaide desalination plant project $26 million claim struck out

Case highlights the need for complex claims to be well considered and particularised before proceeding to litigation.

AustraliaLitigation, Mediation & Arbitration
David Hand
David Hand

On 30 September 2011 the Supreme Court of Victoria in the decision of SMEC Australia Pty Ltd v McConnell Dowell Constructors (Aust) Pty Ltd (No2) [2011] VSC 492 struck out a $26 million claim for variations, extra work, delay costs and misrepresentations by the design team on the Adelaide Desalination Plant Project. While the claim may be redrawn, this is an extraordinary step. It highlights the need for complex claims to be well considered and particularised before proceeding to litigation. With the prospect of litigation between SA Water and AdelaideAqua looming, the future of this project will be one to watch with interest.

ADELAIDE DESALINATION PLANT PROJECT

On 16 February 2009 SA Water entered into a DBOM contract with the 'AdelaideAqua' consortium (consisting of McConnell Dowell Constructors (Aust) Pty Ltd, Abigroup Contractors Pty Ltd, Acciona Aqua Australia Pty Ltd) and Trility Pty Ltd (formerly United Utilities)) for the design, construction and

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from