Parties should raise all relevant arguments at first instance, as they may not be able to raise new points on appeal.

AustraliaLitigation, Mediation & Arbitration

The decision of PND Civil Group Pty Ltd v Bastow Civil Constructions Pty Ltd [2017] NSWCA 159 highlights the difficulty of raising new issues on appeal, in so far as a party will (generally) be bound by the way in which it conducted its case at first instance.

The facts

Bastow Civil Constructions Pty Ltd (Bastow) contracted with Ausgrid to undertake work that involved constructing trenches in public roads owned by Gosford City Council (Council), installing cable ducts in those trenches and backfilling and sealing trenches. Bastow subcontracted some of that work to PND Civil Group Pty Ltd (PND).

Bastow claimed that PND's work was defective and sued it in the District Court of New South Wales seeking damages.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

For further information please contact:

Michael Byrnes, Partner
Phone: + 61 2 9233 5544
Email: [email protected]

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from