From 1 July 2018, ipso facto clauses will be ineffective in the event that the other party encounters financial distress.

AustraliaInsolvency/Bankruptcy/Re-Structuring

Most construction contracts provide a right of termination on the occurrence of an insolvency event. An insolvency event is usually defined broadly to include not only actual insolvency, but also those stages leading up to a potential insolvency, including administration and receivership. These clauses are called 'ipso facto' (meaning 'by that very fact or act') as they provide a fact based trigger for termination rather than one based on default.

The main benefit of these ipso facto clauses is that it gives the terminating party freedom to exit a contract as soon as insolvency becomes a real risk, rather than waiting until it actually happens, by which time it is likely to have suffered actual losses as well as having to deal with a contractual counter-party in distress. Such distress can lead to one or more adverse consequences including: