Tem­po­rary Dis­con­for­mi­ty In Build­ing Defects: Myth, Not Law

The ​"tem­po­rary dis­con­for­mi­ty" argu­ment in con­struc­tion dis­putes sug­gests that defec­tive work iden­ti­fied before prac­ti­cal com­ple­tion is not a breach while the builder retains a con­trac­tu­al right...

AustraliaGovernment, Public Sector

The “tem­po­rary dis­con­for­mi­ty” argu­ment in con­struc­tion dis­putes sug­gests that defec­tive work iden­ti­fied before prac­ti­cal com­ple­tion is not a breach while the builder retains a con­trac­tu­al right to rec­ti­fy. NSW courts have con­sis­tent­ly reject­ed this propo­si­tion, con­firm­ing that defec­tive work con­sti­tutes a breach at the time it is performed.

The notion of “tem­po­rary dis­con­for­mi­ty” is some­times advanced in build­ing dis­putes where defec­tive work is iden­ti­fied before prac­ti­cal com­ple­tion or han­dover. Builders will argue that because they retain a con­trac­tu­al right to rec­ti­fy defects, defec­tive work does not amount to a breach until that oppor­tu­ni­ty has passed. On this view, non‑conforming work is said to be mere­ly “tem­po­rary” and there­fore not action­able by the owner.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.