The “temporary disconformity” argument in construction disputes suggests that defective work identified before practical completion is not a breach while the builder retains a contractual right to rectify. NSW courts have consistently rejected this proposition, confirming that defective work constitutes a breach at the time it is performed.
The notion of “temporary disconformity” is sometimes advanced in building disputes where defective work is identified before practical completion or handover. Builders will argue that because they retain a contractual right to rectify defects, defective work does not amount to a breach until that opportunity has passed. On this view, non‑conforming work is said to be merely “temporary” and therefore not actionable by the owner.