Key Points:
Owners and occupiers of premises in which
telecommunications facilities are installed will have limited scope
to resist a carrier that wishes to connect a facility to their
power supply, and to subsequently draw electricity to ensure the
proper functioning of those facilities.
The Supreme Court of New South Wales has given an expansive
interpretation to the powers of carriers under Schedule 3 of the
Telecommunications Act 1997 (Cth) by holding that carriers can
lawfully plug equipment into a power socket and draw electricity on
an ongoing basis without obtaining the consent of the owner or
occupier of the premises.
The decision means that carriers can rely on the maintenance
power under Schedule 3 to draw from the electricity supply within a
building in which their telecommunications facilities are
installed. It represents an important clarification of the law in
this area, and will be of direct relevance to carriers, building
owners, managers and