EPC Contracts In the Australian Renewable Energy Sector – Wind Farms, part 7

Part 7 continues example clauses for use in an EPC contract for a wind farm in the Australian renewable energy sector.

AustraliaEnergy and Natural Resources
  1. Subject to the provisions of this GC [ ], the Contractor is entitled to an extension of time to the Date for Commercial Operation as the Project Company assesses, where a delay to the progress of the Works is caused by any of the following events, whether occurring before, on or after the Date for Commercial Operation:
    1. any act, omission, breach or default by the Project Company, the Project Company?s Representative and their agents, employees and contractors;
    2. a Variation, except where that Variation is caused by an act, omission or default of the Contractor or its Subcontractors, agents or employees;
    3. a suspension of the Works pursuant to GC [ ], except where that suspension is caused by an act, omission or default of the Contractor or its Subcontractors, agents or employees;