ARTICLE · 28 OCTOBER 2012

EPC Contracts In The Australian Renewable Energy Sector – Wind Farms, part 6

Part 6 discusses example clauses in an EPC contract, such as testing and completion of a wind farm project in Australia.

AustraliaEnergy and Natural Resources

APPENDIX 1 EXAMPLE CLAUSES

Part I - Performance Testing and Guarantee Regime

1 TESTING

Tests and Inspections

1.1 The Contractor must, at its own expense, carry out at the place of manufacture and/or on the Site all tests and/or inspections of the Equipment and any part of the Works as specified in this Contract or as required by any applicable Laws, and as necessary to ensure the Facility operates safely and reliably under the conditions specified in the Schedule of Scope of Work and the Schedule of Tests. [Appendix 1 should specify all the categories of tests other than the Tests (example: test at manufacturers plant, test on site, functional test etc.)]

1.2 The Contractor must also comply with any other requirements of the Owner in relation to testing and inspection.