(c) Contractor's perspective
The main reason for a contractor insisting on a project company
being subject to an exclusive remedies clause is to have certainty
about its potential liabilities. The preferred position for a
contractor will be to confine its liabilities to what is specified
in the EPC contract. For example, an agreed rate of liquidated
damages for delay and, where relevant, underperformance of the wind
farm. A contractor will also generally require the amount of
liquidated damages to be subject to a cap and for the EPC contract
to include an overall cap on its liability.
(d) Project company's perspective
The preferred position for a project company is for it not to be
subject to an exclusive remedies clause. An exclusive remedies
clause limits the project company?s right to recover for any
failure of the contractor to fulfil its contractual obligations to
those remedies specified in the EPC contract. For this reason, an
exclusive remedies clause is