ARTICLE · 28 OCTOBER 2012

EPC Contracts In The Australian Renewable Energy Sector – Wind Farms, part 5

Part 5 continues to discuss key general clauses and dispute resolution provisions in an EPC contract for a wind farm.

AustraliaEnergy and Natural Resources

(c) Contractor's perspective

The main reason for a contractor insisting on a project company being subject to an exclusive remedies clause is to have certainty about its potential liabilities. The preferred position for a contractor will be to confine its liabilities to what is specified in the EPC contract. For example, an agreed rate of liquidated damages for delay and, where relevant, underperformance of the wind farm. A contractor will also generally require the amount of liquidated damages to be subject to a cap and for the EPC contract to include an overall cap on its liability.

(d) Project company's perspective

The preferred position for a project company is for it not to be subject to an exclusive remedies clause. An exclusive remedies clause limits the project company?s right to recover for any failure of the contractor to fulfil its contractual obligations to those remedies specified in the EPC contract. For this reason, an exclusive remedies clause is

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from