EPC Contracts In The Australian Renewable Energy Sector – Wind Farms, part 4

Part 4 discusses drafting liquidated damages clauses and other key general clauses in an EPC contract for a wind farm.

AustraliaEnergy and Natural Resources

Drafting of liquidated damages clauses

Given the role liquidated damages play in ensuring EPC contracts are bankable, and the consequences detailed above of the regime not being effective, it is vital to ensure they are properly drafted to ensure contractors cannot avoid their liquidated damages liability on a legal technicality.

Therefore, it is important, from a legal perspective, to ensure DLDs and PLDs are dealt with separately. If a combined liquidated damages amount is levied for late completion of the works, it risks being struck out as a penalty because it will overcompensate the project company. However, a combined liquidated damages amount levied for underperformance may under compensate the project company.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from