Employers' Right To Recover Costs Of Rectification Works Dented But Not Demolished By Defects Liability Clause

Shepherd and Wedderburn
Shepherd and Wedderburn
Contributor
Shepherd and Wedderburn

Shepherd and Wedderburn

We are an independent law firm, headquartered in Scotland, delivering high-quality legal advice and...

View firm profile
Explore more from Shepherd and Wedderburn

The English common law trend of allowing the recovery of damages for rectification of defects even where the defects liability period remains ...

United KingdomLitigation, Mediation & Arbitration

The English common law trend of allowing the recovery of damages for rectification of defects even where the defects liability period remains ongoing has been followed in a recent judgement from the High Court of Singapore in Thio Keng Thay v Sandy Island Pte Ltd [2019] SGHC 175. It is likely this approach would be mirrored by the Scottish and English courts and so this decision serves as a valuable reminder to UK-based employers that if they unreasonably prevent the contractor from carrying out rectification, and engage an alternative contractor to carry out the works, the quantum of damages recoverable will be limited.

Facts

Thio Keng Thay (the plaintiff) purchased a luxury residential property from Sandy Island Pte Limited (the defendant). After taking possession of the property, the plaintiff discovered a total of 492 alleged defects, including significant water damage, of which approximately 200 were accepted by the defendant. The plaintiff elected to employ a

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from