In the case of RGB Plastering Limited v Tawe Drylining and Plastering Limited the TCC considered the validity of an application for payment under the terms of the subcontract between the parties. In particular, the court determined whether or not the application could be relied on to recover monies in the absence of any Payment Notice or Pay Less Notice, in true "smash and grab" style. The case serves as a useful reminder of the importance of adhering to contractual payment terms.

The Facts

RGB Plastering Limited (RGB) engaged Tawe Drylining (Tawe) as the drylining subcontractor on a project in Portsmouth. The subcontract set out a system for interim payments in clause 18 of the terms and conditions and in the payment schedule. The latter included a table setting out the relevant dates for each payment cycle. These included for the April 2019 cycle that Tawe should issue its application on 28th of that month and the valuation or due date for such an application was

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from