On 19 September 2019, the Ministry of Industry and Trade of
Vietnam ("MOIT") submitted to the Government the final
draft decision of the Prime Minister on the mechanism for
encouraging the development of solar power projects in Vietnam from
1 July 2019 to 31 December 2021 ("FIT2"). It is expected
that the new solar FiT2 decision will be issued soon this
month.
Notably, the final FiT2 draft aims mostly at encouraging solar
power project development in southern area as the MOIT estimated an
addition capacity of approx. 6-8 GW need to be realized to satisfy
major power demand of this area up to 2021.
New FITs for Solar Power Projects – from 1 July 2019 to
31 December 2021
Compared to the previous drafts, the final FIT2 draft does not
determine FiT prices based on regions but only on technology types.
The final FIT2 draft classified solar power projects into three
groups as follows: