ARTICLE · 17 JANUARY 2017

Issues Related To Siting Renewable Generation Near Military Installations In Texas

In addition, the DOD Siting Clearinghouse has an early informal consultation process that can alert project developers to military concerns prior to filing for official FAA feedback.

United StatesTax

Military concerns about siting renewable generation projects near aviation bases have gained traction in Texas, prompting a recent change to the Electric Reliability Council of Texas (ERCOT) interconnection study process and proposed state legislation that would jeopardize property tax abatement eligibility for Texas wind projects within 30 miles of military aviation facilities. According to the Department of Defense (DOD), siting concerns generally relate to the potential for a project to interfere with radar communication, airspace and training operations.1

New ERCOT Requirement for Interconnection Studies

In response to a request from the Texas Governor's Office and the Department of Defense, ERCOT adopted Planning Guide Revision Request 47 (PGRR 47), which became effective November 1, 2016. PGRR 47 resulted in an ERCOT protocol change that requires new generation seeking a Full Interconnection Study (FIS) to submit a declaration to ERCOT concerning the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from