ARTICLE · 10 JULY 2026

What Massachusetts Contractors And Developers Can Learn From Cannistraro v. Columbia Construction

Seyfarth Shaw LLP
Seyfarth Shaw LLP
Contributor
Seyfarth Shaw LLP

Seyfarth Shaw LLP

Our high-caliber legal representation and advanced delivery capabilities allow us to take on our...

View firm profile
Explore more from Seyfarth Shaw LLP

On June 26, 2026 the Massachusetts Supreme Judicial Court issued its decision in J.C. Cannistraro, LLC v. Columbia Construction Co.—a holding that sits at the intersection of Prompt Pay Act compliance...

United StatesReal Estate and Construction

Introduction

On June 26, 2026 the Massachusetts Supreme Judicial Court issued its decision in J.C. Cannistraro, LLC v. Columbia Construction Co.—a holding that sits at the intersection of Prompt Pay Act compliance and the Massachusetts Arbitration Act.1

Most already know that the Massachusetts Prompt Pay Act (PPA) imposes strict timing and certification requirements for rejecting payment applications and proposed change orders on projects valued at $3 million or more. Most notably, the PPA requires the paying party to give the payee written notice of its approval or rejection of progress applications and proposed changes within 15 days of receipt, which notice must include a “factual and contractual basis for the rejection” and must be “certified as made in good faith.”2 In the absence of a timely certified notice, payment is “deemed to be approved” unless the payor properly rejects payment before it comes due.3 

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from