Wadsworth v. Regional Rail Partners — Verified Statements Of Claim Under The Colorado Public Works Act

Higgins, Hopkins, McLain & Roswell, LLC
Explore more from Higgins, Hopkins, McLain & Roswell, LLC

The Colorado Supreme Court has reversed a significant Court of Appeals decision regarding verified statements of claim under the Public Works Act, fundamentally changing what contractors...

United StatesReal Estate and Construction

Editor’s Note: Wadsworth Revisited

In August 2024, following the Colorado Court of Appeals’ decision in Ralph L. Wadsworth Construction Company, LLC v. Regional Rail Partners, we published Colorado Court of Appeals’ Ruling Highlights Dangers of Excessive Public Works Claims.

At the time, the decision warranted a significant warning to contractors and subcontractors performing public work in Colorado. The Court of Appeals concluded that Wadsworth’s verified statement of claim improperly included unliquidated delay damages and that, because the claim was excessive, Wadsworth forfeited its right to recover the amounts included in the claim. We cautioned contractors to carefully scrutinize verified statements of claim and to avoid including unliquidated damages or amounts that were not yet due and payable.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from