ARTICLE · 27 OCTOBER 2026

Colorado’s New Retainage Bond Law: Can General Contractors Contract Around It?

Higgins, Hopkins, McLain & Roswell, LLC
Explore more from Higgins, Hopkins, McLain & Roswell, LLC

Colorado’s General Assembly has once again changed the rules governing retainage on private construction projects. With the passage of House Bill 26-1311, effective August 12, 2026, contractors and subcontractors now have a statutory mechanism to substitute a qualifying surety bond for cash retainage.

United StatesCorporate/Commercial Law

HB 26-1311 gives contractors and subcontractors a new way to recover cash retainage. But can that statutory right be waived in a construction contract?

Colorado’s General Assembly has once again changed the rules governing retainage on private construction projects. With the passage of House Bill 26-1311, effective August 12, 2026, contractors and subcontractors now have a statutory mechanism to substitute a qualifying surety bond for cash retainage.

Colorado’s construction industry has long struggled with the timing of retainage payments, particularly for subcontractors whose work is completed early in a project. Although Colorado’s 2021 legislation generally limited retainage to five percent on covered private construction contracts, it did not establish a corresponding deadline for releasing those funds. Indeed, C.R.S. § 38-46-103(2) expressly preserved contractual provisions governing payment timing, including final payment and conditions precedent to payment. As a result,

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from