The Miller Act has a strict requirement that subcontractors that
do not have a direct contract with the general contractor must
provide notice of nonpayment to the general contractor within 90
days.
An appeals decision by the Seventh Circuit underscores the
importance of strict adherence to the requirements of the Miller
Act. A&C Construction & Installation, Co. WLL v. Zurich
American Insurance Company and The Insurance Company of the State
of Pennsylvania, No. 19-3325, decided June 30, 2020, concerns
a Miller Act claim on a payment bond by a subcontractor on a
federal construction project. Section 3133 of The Miller Act, 40
U.S.C. §3133(b), requires a payment bond and a performance
bond to be posted on construction contracts in excess of $100,000
with the federal government. A&C Construction was a second-tier
subcontractor on a project for the U.S. Army Corps of Engineers on
a Qatar air base. A&C in turn subcontracted a part of its work
to RNC, a third-tier