The IRS Large Business and International (LB&I) Division is
currently pursuing a "compliance campaign" against large
land developers of residential communities for improper use of the
more taxpayer-friendly completed contract method (CCM) of
accounting. The IRS believes that some developers are deferring
profits under the CCM that should be recognized — and taxed
— earlier.
The Issue
For federal income tax purposes, long-term contracts are those
that span a year end. For example, if you enter into a contract on
December 29, but do not complete work until January 20, you have a
long-term contract.
The CCM allows developers to defer the recognition of taxable
income and expense until the year a long-term construction contract
is completed and accepted by the customer. That way, the profit is
not taxed until the year the project is completed.