Mind The Gap! – A Potential Carve-Out In The Strict Notice Requirements Under The Virginia Public Procurement Act

Fox Rothschild LLP
Fox Rothschild LLP
Contributor
Fox Rothschild LLP

Fox Rothschild LLP

Who We Are With bold growth, Fox Rothschild brings together 1,000 attorneys coast to coast. We...

View firm profile
Explore more from Fox Rothschild LLP

Despite the Virginia Public Procurement Act’s (VPPA) strict and rigorous notice requirements for contract claims against a public entity, the highly factual inquiry necessary to assess compliance can get contractors past a motion to dismiss.

United StatesReal Estate and Construction

Despite the Virginia Public Procurement Act's (VPPA) strict and rigorous notice requirements for contract claims against a public entity, the highly factual inquiry necessary to assess compliance can get contractors past a motion to dismiss. Last month, the U.S. District Court for the Western District of Virginia (WDVA) confirmed that whether or a not notice complies with the VPPA's requirements is a question of fact to be determined at trial, not on a motion to dismiss. Specifically, WDVA denied the City of Charlottesville's motion to dismiss Costello Construction of Maryland, Inc.'s cumulative impact claims against the City on the basis of untimely notice under the VPPA. At issue in the City's motion was the following language of the VPPA, requiring notice of contractual claims to the public entity: 