ARTICLE · 21 APRIL 2015

Government’s Bad Faith Material Breach Justifies Work Stoppage

In the recent decision Kiewit-Turner v. Department of Veterans Affairs, the CBCA held that the Department of Veterans Affairs materially breached its contract with its contractor, Kiewit-Turner.

United StatesReal Estate and Construction

In the recent decision Kiewit-Turner v. Department of Veterans Affairs, the Civilian Board of Contract Appeals ("CBCA"), the judicial body with authority over claims against the non-military agencies of the United States Government, held that the Department of Veterans Affairs ("VA") materially breached its contract with its contractor, Kiewit-Turner ("KT"), by failing to provide a design that could be built for the estimated construction cost at award ("ECCA"). The CBCA ruled that as a result of the material breach, KT was permitted to stop performance.

In August 2010, VA awarded KT an IDC-type contract (integrated design and construct) for preconstruction services on a medical center in Colorado. The contract contained an option for the performance of construction services. The contract was intended to allow KT to review and advise VA on its design, allowing VA to procure additional funds or direct its architect-engineer ("AE") to make changes to meet the ECCA.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from