General Motors is committed to sourcing 100 percent of its U.S.
facilities with renewable energy by 2030, leading to an
all-electric, zero-emissions future. GM's Ultium Cells LLC
manufacturing facility, constructed in Lordstown, Ohio, is
reflective of the organization's
commitment. Taft's Lean Construction & Integrated
Project Delivery (IPD) team, alongside selected project
contractors, collaborated to execute the trailblazing
project.
The Challenge
The project involves the design and construction of a
nearly three-million-square-foot plant that will
mass-produce battery cells for electric vehicles. This
approximately $2.3 billion manufacturing facility, a joint
venture between General Motors and LG Chem of South Korea, is
critical to GM's vision of producing all-electric vehicles by
2030. The ambitious construction project came with many
complexities - along with a need to maximize value and minimize
waste.