Introduction: More Than Just a Contract Requirement
Construction schedules take many forms, ranging from simple bar or Gantt charts to fully developed Critical Path Method (CPM) schedules prepared using tools such as Primavera P6 or Microsoft Project. Regardless of format, initially the schedule is intended to represent how the contractor plans to execute the work, but it can also be used to measure and evaluate delays and changes in the work.
Construction schedules are routinely required by contract, but their true importance often does not become apparent until a dispute arises. In litigation, including trials and arbitrations, schedules — particularly the baseline and contemporaneous updates — frequently become the primary evidence used to determine whether delays occurred, who caused them, whether a time extension for the contractor is warranted, as well as how much time or money is at stake. Courts and tribunals rely heavily on schedules to assess credibility, causation,