Share on LinkedInShare on LinkedIn

ARTICLE · 26 APRIL 2011

Build For The Tenant, But Lien The Landlord's Title? Massachusetts Supreme Judicial Court Clarifies The Standard

Duane Morris LLP
Duane Morris LLP
Contributor
Explore more from Duane Morris LLP

The Massachusetts Supreme Judicial Court (the "SJC") released a decision on April 13, 2011—in Trace Construction v. Dana Barros Sports Complex—that clarifies a contractor's lien rights against a landlord when the contractor performed work for the tenant.

United StatesReal Estate and Construction

The Massachusetts Supreme Judicial Court (the "SJC") released a decision on April 13, 2011—in Trace Construction v. Dana Barros Sports Complex1—that clarifies a contractor's lien rights against a landlord when the contractor performed work for the tenant. The decision is likely to have significant ramifications for contractors doing tenant work. As in many cases, this one arose when one company folded—the tenant here.

The Dana Barros2 Sports Complex LLC signed a lease with Oxford Road Realty Trust for indoor commercial space, to turn the space into a basketball camp facility. Barros advised Oxford that he intended to renovate the premises, and the lease provided that all renovations would become the property of Oxford at the end of the lease period. Barros was required to obtain Oxford's consent for any alteration of the building. Barros signed contracts with Trace Construction ("Trace") and CB Seating. Trace had several subcontractors.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from