Practical Considerations Under FIDIC Contracts In Light Of COVID-19

Sheppard
Sheppard
Contributor
Sheppard

Sheppard

Businesses turn to Sheppard to deliver sophisticated counsel to help clients move ahead. With more...

View firm profile
Explore more from Sheppard

The outbreak of the coronavirus has been an unprecedented event affecting every industry, including construction. To ensure their entitlement to an extension of time, costs, or even termination,...

United StatesLitigation, Mediation & Arbitration

The outbreak of the coronavirus has been an unprecedented event affecting every industry, including construction.  To ensure their entitlement to an extension of time, costs, or even termination, parties to construction contracts need to carefully review the contract provisions that allocate risks.  Below, we discuss a number of practical considerations that may arise under a standard form construction contract – such as the FIDIC Red Book – in light of the COVID-19 pandemic.

A. Is the outbreak of coronavirus a force majeure event under FIDIC contracts?

The COVID-19 pandemic qualifies as a force majeure event under the 2017 FIDIC Red Book.  Pursuant to Clause 18 of the Red Book, a force majeure event is an event that is (1) beyond the parties' control, (2) was not reasonably foreseeable, (3) could not reasonably have been avoided once having arisen, and (4) was not substantially attributable to either party.  While global pandemics are not specifically listed among

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from