CDP Applicant May Not Challenge Local Agency's CEQA Decision On Coastal Development Permit While CDP Appeal To Coastal Commission Is Pending

Sheppard
Sheppard
Contributor
Sheppard

Sheppard

Businesses turn to Sheppard to deliver sophisticated counsel to help clients move ahead. With more...

View firm profile
Explore more from Sheppard

In Fudge v. City of Laguna (G055711), published on February 13, 2019, the Fourth District Court of Appeal joined the First and Sixth Districts by reaffirming the need for a litigant to wait

United StatesLitigation, Mediation & Arbitration

In Fudge v. City of Laguna (G055711), published on February 13, 2019, the Fourth District Court of Appeal joined the First and Sixth Districts by reaffirming the need for a litigant to wait for the California Coastal Commission's ("Commission") determination on the appeal of a coastal development permit ("CDP") prior to initiating litigation.

The key takeaway here is that a local agency's California Environmental Quality Act ("CEQA") determination in cases where a CDP has been appealed is not final for purposes of adjudication if the Commission has not ruled on the appeal. While the exhaustion of administrative remedies doctrine is well established, this decision is unique in that it applies the doctrine even where a judicial challenge alleges only CEQA violations, providing insight into the relationship between CEQA and the Coastal Act. Moreover, this decision also addresses the extent to which the Commission's standard of review is de novo.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from