In Fudge v. City of Laguna (G055711), published on
February 13, 2019, the Fourth District Court of Appeal joined the
First and Sixth Districts by reaffirming the need for a litigant to
wait for the California Coastal Commission's
("Commission") determination on the appeal of a coastal
development permit ("CDP") prior to initiating
litigation.
The key takeaway here is that a local agency's California
Environmental Quality Act ("CEQA") determination in cases
where a CDP has been appealed is not final for purposes of
adjudication if the Commission has not ruled on the appeal. While
the exhaustion of administrative remedies doctrine is well
established, this decision is unique in that it applies the
doctrine even where a judicial challenge alleges only CEQA
violations, providing insight into the relationship between CEQA
and the Coastal Act. Moreover, this decision also addresses the
extent to which the Commission's standard of review is de
novo.