In its Memorandum Order, the Court adopted the plaintiff's proposed construction of the term in dispute.

United StatesIntellectual Property

By Memorandum Order entered by The Honorable Gregory M. Sleet in Merck Sharp & Dohme B.V. v. Warner Chilcott Company, LLC, Civil Action No. 13-2088-GMS (D.Del., February 25, 2016), the Court rendered its construction of the term "physiologically required amounts," which remained in dispute in U.S. Patent No. 5,989,581 ( "the '581 patent") during the four-day bench trial. In its Memorandum Order, the Court adopted the plaintiff's proposed construction of the term in dispute.

A copy of the Memorandum Order is attached.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from