A recent decision from the United States Court of Federal Claims
(COFC) sets forth the standard for when the government's
failure to make a decision on a certified claim will be considered
a deemed denial. In Rudolph and Sletten, Inc. v. U.S.,
the COFC clarified the Contract Disputes Act (CDA) timing
requirement for the government to issue a decision on a certified
claim.
In Rudolph and Sletten, the
contractor, Rudolph and Sletten (R&S), submitted a certified
claim seeking a time extension and additional costs related to a
contract for the construction of the Southwest Fisheries Science
Center Replacement Headquarters and Laboratory in La Jolla,
California. R&S originally submitted its certified claim on
August 20, 2013. On October 21, 2013, the contracting officer
advised R&S that, given the complexity of the claim, he would
need additional time to issue a decision and advised that a
decision would be made within nine months. R&S then requested
that the