ARTICLE · 04 JUNE 2015

When Govt. Failure To Issue Final Decision On Certified Claim Is A Deemed Denial

The court's decision in Rudolph and Sletten will serve as an important resource for contractors.

United StatesGovernment, Public Sector

A recent decision from the United States Court of Federal Claims (COFC) sets forth the standard for when the government's failure to make a decision on a certified claim will be considered a deemed denial. In Rudolph and Sletten, Inc. v. U.S., the COFC clarified the Contract Disputes Act (CDA) timing requirement for the government to issue a decision on a certified claim.

In Rudolph and Sletten, the contractor, Rudolph and Sletten (R&S), submitted a certified claim seeking a time extension and additional costs related to a contract for the construction of the Southwest Fisheries Science Center Replacement Headquarters and Laboratory in La Jolla, California. R&S originally submitted its certified claim on August 20, 2013. On October 21, 2013, the contracting officer advised R&S that, given the complexity of the claim, he would need additional time to issue a decision and advised that a decision would be made within nine months. R&S then requested that the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from