Wait Too Long And You Might Miss Sum-Thing: ASBCA Again Underscores That Failure To Timely Raise Sum-Certain Defense Can Result In Forfeiture Under New Federal Circuit Precedent

Crowell & Moring LLP
Crowell & Moring LLP
Contributor
Crowell & Moring LLP

Crowell & Moring LLP

Crowell & Moring’s Doha office is a full service legal practice that serves as the firm’s regional...

View firm profile
Explore more from Crowell & Moring LLP

On remand from the U.S. Court of Appeals for the Federal Circuit, in ECC International Constructors, LLC, ASBCA Nos. 59586, 59643, the Armed Services Board of Contract Appeals...

United StatesGovernment, Public Sector

On remand from the U.S. Court of Appeals for the Federal Circuit, in ECC International Constructors, LLC, ASBCA Nos. 59586, 59643, the Armed Services Board of Contract Appeals concluded that, by waiting until after a hearing on the merits and six years after the appeal was filed, the government forfeited its right to challenge the contractor's satisfaction of the FAR's sum-certain requirement for Contract Disputes Act claims.

As we previously discussed, the decision of the Federal Circuit in ECC Int'l Constructors Inc. v. Army reversed longstanding precedent that a claim must state a "sum certain" for a board or court to exercise jurisdiction over an appeal. The underlying appeal dated back to 2014, but the government chose to wait until 2020, after earlier negotiations and a nine-day merits hearing, to challenge the Board's jurisdiction. Pointing to decades of caselaw, the ASBCA dismissed the contractor's claim for lack of jurisdiction because the claim had

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from