The Civilian Board of Contract Appeals (CBCA or Board) recently released its remand decision in Eagle Peak Rock & Paving, Inc. v. Department of Transportation...

United StatesGovernment, Public Sector

The Civilian Board of Contract Appeals (CBCA or Board) recently released its remand decision in Eagle Peak Rock & Paving, Inc. v. Department of Transportation, CBCA 7832(5692)-REM, after the Federal Circuit reversed its prior decision for applying the incorrect standard of review for contract terminations. This appeal offers important lessons to contractors on how to effectively challenge a termination: most importantly, contemporaneously document events pertinent to the termination and apply the de novo standard when seeking Board or court review.

The underlying contract was for road improvement in Yellowstone National Park. Shortly after contract award, Eagle Peak submitted a preliminary schedule, and then several months later, after the Federal Highway Administration (FHWA or agency) issued a cure notice raising concerns with that schedule, multiple revised schedules. The agency alternatingly either did not respond to the revised schedules or responded with vague

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from