Size Protest Timing: How To Manage Deadlines And Save Your Protest Or Appeal

Fox Rothschild LLP
Fox Rothschild LLP
Contributor
Fox Rothschild LLP

Fox Rothschild LLP

Who We Are With bold growth, Fox Rothschild brings together 1,000 attorneys coast to coast. We...

View firm profile
Explore more from Fox Rothschild LLP

The appeal at issue arose out of a small business size protest (filed by KEMRON Environmental Services Inc.) that was denied by the SBA on May 11, 2015.

United StatesGovernment, Public Sector

We often look at GAO bid protest timing as a complex and strictly enforced issue.  Today: a reminder that all protests – including size protests filed with the Small Business Administration – carry deadlines with the potential to end your protest before it even begins.

Traditional SBA size protests have two primary deadlines:

  • In order to be considered timely, size protests of negotiated procurements (including protests on partial set-asides and reserves of Multiple Award Contracts and set-asides of orders against Multiple Award Contracts) must be received by the contracting officer prior to the close of business on the 5th day (exclusive of Saturdays, Sundays, and legal holidays) after the contracting officer has notified the protestor of the identity of the prospective awardee.