The US government recently learned that, in addition to its customary liability for having given a contractor defective specifications, where those defective specs prompt a relator's frivolous FCA case, ...

United StatesGovernment, Public Sector

The US government recently learned that, in addition to its customary liability for having given a contractor defective specifications, where those defective specs prompt a relator's frivolous False Claims Act (FCA) case, the government will also owe the contractor's defense costs when it does not promptly intervene to dismiss the action. The Court of Federal Claims found those defense costs allowable, even under a fixed price contract.

In The Tolliver Group, Inc. v. United States, No. 17-1763C (Ct. Claims 2020), the court considered a fixed-price, level-of-effort contract (with a $1.41 million ceiling) to produce technical manuals for an Army mine clearing vehicle. The Project Work Statement required the Army to provide Tolliver a technical data package (TDP), including the vehicle manufacturer's engineering drawings, so Tolliver would not need to reverse engineer the machine. The Army failed to deliver the TDP, but still directed Tolliver to perform. Only after

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from