Recent Federal Circuit Decision Highlights Important Takeways For Contractors

Fox Rothschild LLP
Fox Rothschild LLP
Contributor
Fox Rothschild LLP

Fox Rothschild LLP

Who We Are With bold growth, Fox Rothschild brings together 1,000 attorneys coast to coast. We...

View firm profile
Explore more from Fox Rothschild LLP

The United States Court of Appeals for the Federal Circuit recently issued an important decision that highlights a few important takeaways for all government contractors!

United StatesGovernment, Public Sector

The United States Court of Appeals for the Federal Circuit recently issued an important decision – K-Con Building Systems, Inc. v. United States, Case No. 2014-5062 – that highlights a few important takeaways for all government contractors!

Background

K-Con Building Systems, Inc. (K-Con) entered into a contract to construct a building for the United States Coast Guard.  After a delay in contract completion, the federal government imposed liquidated damages (or LDs).  K-Con presented three discrete claims against the federal government in the Court of Federal Claims: (1) remission of LDs on the grounds that the LDs clause was unenforceable, (2) remission of LDs on the grounds that K-Con was entitled to a time extension, and (3) additional compensation for constructive changes.