Recent Dispute Between Teaming Partners Teaches Lessons About Drafting Protest Provisions In Teaming Agreements

A Florida federal court has ruled that a teaming agreement for a government contract did not compel an unsuccessful prime contractor to protest a lost award...

United StatesGovernment, Public Sector

Thomas M. "Tom" Brownell is a Partner in our Tysons office.

David S. Black is a Partner in our Tysons office .

A Florida federal court has ruled that a teaming agreement for a government contract did not compel an unsuccessful prime contractor to protest a lost award, despite the demand by its subcontractor teaming partner. TYR Tactical, LLC v. Protective Products Enterprises, LLC and Point Blank Enterprises, Inc., Case No. 0:15-cv-061741 (S.D. Fla., Oct. 13, 2016). The decision shows some of the challenges involved when drafting and negotiating provisions of teaming agreements intended to address the parties' roles and responsibilities with respect to possible protests if the team is not successful.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from