Overview
On April 30, 2026, President Trump signed an Executive Order (EO) titled “Promoting Efficiency, Accountability, and Performance in Federal Contracting,” directing executive branch agencies to make fixed-price contracts the default and preferred method of federal procurement. But the EO not only establishes a priority for fixed-price contracts; it mandates renegotiation of the 10 largest existing cost-type contracts at each agency within 90 days. This advisory covers the EO’s key terms and likely impacts, highlighting what remains to be seen regarding the impacts on federal contractors.
Background
Federal procurement is accomplished through a spectrum of contract types falling along a risk-allocation continuum: whereas fixed-price contracts place performance risk primarily on the contractor by requiring delivery of defined outcomes for a set price, cost-reimbursement contracts shift financial risk to the government by guaranteeing recovery of contractors’ allowable incurred