Notable Contract Clauses & Considerations For Contractors And Grantees Facing Regulatory Shifts Based On Priorities Of The New Administration

Considering recent events, we have prepared a comprehensive, side-by-side analysis of critical contract clauses and other considerations for contractors and grantees seeking to address any updates to their agreements.

United StatesGovernment, Public Sector

Considering recent events, we have prepared a comprehensive, side-by-side analysis of critical contract clauses and other considerations for contractors and grantees seeking to address any updates to their agreements. The guide covers stop-work directives, suspensions, terminations, payment delays, and tariff increases — highlighting specific provisions and timelines essential for protecting rights and pursuing potential cost recovery. View the complete guide below:

Contractors Grantees
Direction to Stop-Work or Suspending the Contract Affected contractors should review the terms of the clauses in their contract that may provide the government to suspend performance (e.g., FAR 52.242-14) or issue a stop-work order (e.g., FAR 52.242-15) for limits associated with this kind of direction, such as the government's inability to issue a stop-work order for longer than 90 days (unless agreed-to by the contractor) or due dates for the contractor's notice

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from