ARTICLE · 10 JULY 2024

Inconsistencies Between An Offeror's Technical Proposal And Price Proposal Can Only Be Resolved In The Agency's Discretion If The Solicitation Allows

In a decision released on June 18, 2024, the Government Accountability Office (GAO) found for a protester who argued that an awardee's technical proposal...

United StatesGovernment, Public Sector

In a decision released on June 18, 2024, the Government Accountability Office (GAO) found for a protester who argued that an awardee's technical proposal and price proposal contained inconsistencies that could not be resolved in the agency's discretion. BAE Sys. Tech. Sol'ns & Servs., Inc., B-420860.4 et al., June 18, 2024.

The awardee's technical proposal provided that they would compensate certain high demand personnel at an above-average rate, while the awardee's revised price proposal offered average or below-average rates to those same personnel. This inconsistency was fatal to the awardee's defense against the protest.

The awardee was initially a protester. The GAO sustained the awardee's initial protest and recommended a reevaluation of proposals. Id. at 2. For its part, the agency requested the submission of updated cost proposals. Id. However, the agency further advised that no updates to any other proposals were allowed. Id.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from