ARTICLE · 03 OCTOBER 2014

Fraud Claim Arises from Intentionally Undervalued Contract Extension that the Government Approved – Incumbent Contractors Beware

Fox Rothschild LLP
Fox Rothschild LLP
Contributor
Fox Rothschild LLP

Fox Rothschild LLP

Who We Are With bold growth, Fox Rothschild brings together 1,000 attorneys coast to coast. We...

View firm profile
Explore more from Fox Rothschild LLP

Veridyne Corp., an 8(a) small business concern, was subject to fraud and false statement claims by the U.S. Department of Transportation (UDOT) for undervaluing an estimate to perform a task order contract extension.

United StatesGovernment, Public Sector

Veridyne Corp., an 8(a) small business concern, was subject to fraud and false statement claims by the U.S. Department of Transportation (UDOT) for undervaluing an estimate to perform a task order contract extension.  The Federal Circuit recently denied Veridyne's request for payment of approximately $1 million claimed owed under the task order.  See Veridyne Corp. v. U.S., Case No. 13-5011.  UDOT was aware of, and encouraged the undervalued estimate from the contractor, and the contractor was still held liable for its actions.

Veridyne obtained the task order by convincing UDOT to award it a $3 million task order extension that would cover several years after it was due to graduate from the 8(a) program.  A contract award larger than $3 million would have required that the procurement be opened for full and fair competition, which would have delayed an award to Veridyne to the point it was no longer eligible for small-business set-asides.  Both Veridyne and UDOT