On Dec. 23, 2020, the Federal Circuit published its decision in
BGT Holdings LLC v. United States, 984 F.3d 1003, holding
that the government's refusal to adequately consider a
contractor's request for equitable adjustment (REA) could be
considered a breach of contract. In this case, BGT Holdings LLC
(BGT) was appealing a dismissal of its claims by the Court of
Federal Claims (COFC) in a dispute with the Navy.
BGT was performing a fixed-price contract to build and deliver a
gas turbine generator for the Navy. As part of its performance, BGT
was to receive and incorporate certain government-furnished
equipment (GFE) into its deliverable. Well into performance, the
Navy cancelled two of the GFE items, requiring BGT to purchase them
on the open market. BGT filed an REA to recoup the costs to
purchase the cancelled GFE, consistent with FAR §
52.245-1(d)(2)(i), Government Property and FAR § 52.243-1,
Changes – Fixed-Price. The Navy rejected the REA.