ARTICLE · 21 JULY 2015

Contractor Barred From Using The "Total Cost" Or "Modified Total Cost" Approach To Establish Delay Claim

In a recent ruling, Hill York Service Corporation v. Critchfield Mechanical, Inc., the U.S. District Court for the Southern District of Florida held that a contractor may not establish damages for delay...

United StatesGovernment, Public Sector

In a recent ruling, Hill York Service Corporation v. Critchfield Mechanical, Inc., the U.S. District Court for the Southern District of Florida held that a contractor may not establish damages for delay under either the "total cost" approach or the "modified total cost" approach when there is evidence attributing some of the delay to the contractor, and no apportionment of the costs has been made for the contractor's delays.

Critchfield Mechanical, Inc. ("CMI") was a mechanical contractor on the Air Force Technical Applications Center project ("the Project") at Patrick Air Force Base in Florida. The Project involved the design and construction of four separate facilities at the Base, including a headquarters building, a process support and laboratory building, a central utility plant, and an underground utility vault. CMI was responsible for creating and delivering to the Project certain major mechanical equipment, including air handling units that were to be set on

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from