The COFC recently issued a decision in Kansas City Power & Light Co. v. United States, No. 15-348C (May 9, 2019) addressing a critical Federal Circuit decision interpreting the statute of limitations under the CDA ...

United StatesGovernment, Public Sector

The Court of Federal Claims (COFC) recently issued a decision in Kansas City Power & Light Co. v. United States, No. 15-348C (May 9, 2019) addressing a critical Federal Circuit decision interpreting the statute of limitations under the Contract Disputes Act (CDA) that impacts the time by which contractors must file claims. Simultaneously, the COFC blurred the lines of the continuing claims doctrine, a partial defense to application of the statute of limitations.

The CDA requires any party seeking relief under a government contract to file a claim within six years of claim accrual. 41 U.S.C. 7103(a)(1), (4). A claim accrues on "the date when all events, that fix the alleged liability of either the government or the contractor and permit assertion of the claim, were known or should have been known. For liability to be fixed, some injury must have occurred. However, money damages need not have been incurred." FAR 33.201. On the question of injury, the case law had

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.