The Court of Federal Claims (COFC) recently issued a decision in
Kansas City Power & Light Co. v. United States, No.
15-348C (May 9, 2019) addressing a critical Federal Circuit
decision interpreting the statute of limitations under the Contract
Disputes Act (CDA) that impacts the time by which contractors must
file claims. Simultaneously, the COFC blurred the lines of the
continuing claims doctrine, a partial defense to application of the
statute of limitations.
The CDA requires any party seeking relief under a government
contract to file a claim within six years of claim accrual. 41
U.S.C. 7103(a)(1), (4). A claim accrues on "the date when all
events, that fix the alleged liability of either the government or
the contractor and permit assertion of the claim, were known or
should have been known. For liability to be fixed, some injury must
have occurred. However, money damages need not have been
incurred." FAR 33.201. On the question of injury, the case law
had