Can The Government Assert CAS Noncompliance After Prolonged Audit Delay And Contracts Awarded Based On Disclosed Practices?

Arnold & Porter
Arnold & Porter
Contributor
Arnold & Porter

Arnold & Porter

With over 1,000 lawyers across 16 offices worldwide, Arnold & Porter is renowned for its...

View firm profile
Explore more from Arnold & Porter

Contractors performing work subject to the Cost Accounting Standards ("CAS") often deal with delayed audits, alleged noncompliance determinations and payment demands.

United StatesGovernment, Public Sector

Contractors performing work subject to the Cost Accounting Standards ("CAS") often deal with delayed audits, alleged noncompliance determinations and payment demands. The authors of this article discuss a Court of Federal Claims case, the final decision of which will be of interest to all CAS-covered contractors, as it could limit the government's ability to recoup payments made long ago under contracts that were awarded based upon disclosed accounting practices the government only later deems problematic

Federal contractors performing work subject to the Cost Accounting Standards ("CAS") are all too familiar with delayed audits, alleged noncompliance determinations and payment demands—often arising years after the contractor has been operating under the same, disclosed accounting practices.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from