Share on LinkedInShare on LinkedIn

ARTICLE · 12 NOVEMBER 2024

Bid Protest: Unreasonable And Ambiguous Solicitation Terms Sink Procurements

Crowell & Moring LLP
Crowell & Moring LLP
Contributor
Crowell & Moring LLP

Crowell & Moring LLP

Crowell & Moring’s Doha office is a full service legal practice that serves as the firm’s regional...

View firm profile
Explore more from Crowell & Moring LLP

The term "bid protest" typically calls to mind challenges to an agency's award of a contract. But two recent GAO sustain decisions—Wilson 5 Service Company, Inc., B-422670, Sept. 25, 2024, 2024 CPD...

United StatesGovernment, Public Sector

What You Need to Know

  • Key takeaway #1 When a solicitation is issued, it is essential to engage with bid protest counsel to assist in reviewing the solicitation terms to ensure that they are clear, consistent, and do not contain any improper restriction on your company's ability to compete fairly. Timing is of the essence, as problematic provisions must be addressed before the solicitation closing date.
  • Key takeaway #2 If unable to address problematic solicitation terms via the solicitation's Questions & Answers (Q&A) process, contractors should consider whether a protest could potentially remedy the solicitation flaws.

The term "bid protest" typically calls to mind challenges to an agency's award of a contract. But two recent GAO sustain decisions—Wilson 5 Service Company, Inc., B-422670, Sept. 25, 2024, 2024 CPD ¶ 230 and MAXIMUS Federal Services, Inc., B-422676, Sept. 16, 2024, 2024 CPD ¶ 222—highlight another impactful tool for protecting a contractor's

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from